Before you renovate a co-op or condo, you need written approval from the building. The basis for that approval is the Alteration Agreement — often a long document — plus the building's alteration guidelines and house rules.
Co-op vs. condo
| Co-op | Condo | |
|---|---|---|
| You own | Shares + proprietary lease | The unit itself |
| Approvals | Usually stricter; the board has broad power | Typically lighter, but still required |
| Plan review | Often the building's architect or engineer | The managing agent or its consultant |
Starting work without approval can lead to a stop order, forfeited deposits and an order to restore.
Clauses to read closely
- Scope — approval covers the drawings you submitted; changes need re-approval.
- Work hours — commonly weekdays about 9 to 5, with tighter windows for noisy work.
- Summer work rule — some buildings restrict or ban renovation in summer.
- Wet over dry — many buildings bar kitchens and baths above a neighbor's living or sleeping rooms.
- Insurance — the contractor's certificate of insurance must match the building's limits and additional-insured list exactly.
- Deposits and fees — security deposit, plan review, managing agent and elevator fees.
- Completion deadline — some agreements impose per-day penalties.
- Owner liability — for damage to common areas and neighbors.
- Close-out — permit sign-offs, as-built drawings and other documents.
The typical package
| Document | Prepared by |
|---|---|
| Application and Alteration Agreement | Owner |
| Drawings (plans, demolition, MEP) | Designer / architect (sealed where a permit applies) |
| Contractor license | Contractor |
| Certificates of insurance | Contractor's insurance broker |
| Subcontractor licenses and insurance | Plumber, electrician |
| Asbestos report | Licensed investigator, where required |
| Product specs | Designer (e.g., acoustic underlayment, waterproofing) |
Common sticking points
- Sound: many buildings require acoustic underlayment under hard floors, or a minimum area of carpet. See our soundproofing notes in the FAQ.
- Washer/dryer: older buildings may prohibit them or allow only ventless models.
- Range hoods: most older apartments have no exterior duct; new wall penetrations are rarely approved.
- Electrical capacity: adding induction, ovens or heat pumps may require a service evaluation.
Five ways to get approved faster
- Get the alteration rules before you buy.
- Submit a complete package — missing documents are the number-one delay.
- Have the broker send COIs directly, with additional insureds worded exactly.
- Put waterproofing, underlayment and equipment specs on the drawings.
- Work with the super on elevator bookings, deliveries and debris removal.
Typical review takes 4–12 weeks, plus DOB time where a permit is needed. Plan it with the timeline planner.
General renovation information only. Costs and regulations change — confirm with current official sources, your building and a licensed professional.